Question 001
Time Remaining
一名專案經理正在領導一個處於進階的專案。風險管理計畫中確定的所有高層次風險都已解決,只剩下低層次風險。專案經理現在應該做什麼?
降低專案風險的優先性,因為所有剩餘的風險都是低層次風險。
通知利害關係人,所有的高層次風險都已解決。
重新評估已識別的風險並更新風險登錄表。
將低層次風險重新歸類為高層次風險。
A project manager is leading an advanced project. All high-level risks identified in the risk management plan have been resolved, and only low-level risks remain. What should the project manager do now?
Reduce the priority of project risks because all remaining risks are low-level risks.
Notify stakeholders that all high-level risks have been resolved.
Reassess the identified risks and update the risk register.
Reclassify low-level risks as high-level risks.